Highlights: iRoad I
Updates (Oct 2021)

660

Total Contract Roads

52,114,248,125

Total Contracts Value (LKR)

11

Total Contractors

44

Total Packages
Summary
Completed Rate
 
All Roads
660
Completed
536
Overall Physical Progress
 
Total Km's
2,731.672
Completed
2,071.471
Overall Financial Progress
 
Total Value
52,114.25Mn
Total Paid
48,493.19Mn
Highlights: iRoad II
Updates (Oct 2021)

1327

Total Contract Roads

133,490,016,565

Total Contracts Value (LKR)

23

Total Contractors

59

Total Packages
Summary
Completed Rate
 
All Roads
1327
Completed
371
Overall Physical Progress
 
Total Km's
3,578.225
Completed
985.675
Overall Financial Progress
 
Total Value
133,490.02Mn
Total Paid
73,508.09Mn